Prepare effectively for the MHIC NASCLA Contractors Exam. This comprehensive quiz will test your knowledge with multiple-choice questions and detailed hints for every question. Boost your confidence and ensure you're ready when exam day arrives!

Each practice test/flash card set has 50 randomly selected questions from a bank of over 500. You'll get a new set of questions each time!

Practice this question and more.


In addition to full reimbursement, what is a contractor responsible for paying on the amount needed to reimburse the fund?

  1. 10% interest

  2. 5% interest

  3. No interest

  4. 15% interest

The correct answer is: 10% interest

The contractor is responsible for paying 10% interest on the amount needed to reimburse the fund, providing an incentive for contractors to promptly fulfill their financial obligations. This rate of interest is designed to encourage timely reimbursement while also recognizing the time value of money. When a contractor has to reimburse a fund, the 10% interest acts as a penalty for the delay and ensures that the fund is compensated for the time it takes to resolve the financial liability. This is a common practice within various financial frameworks to maintain the integrity and liquidity of the fund involved. This structure helps to reinforce the idea that contractors carry a significant responsibility for any financial impacts their actions may have on the fund, emphasizing the importance of financial accountability within the construction industry.